Why fight over an interchange none of you paid for? – Franklin Cudjoe quizzes Akufo-Addo, Mahama

President Nana Addo Dankwa Akufo-Addo and Former President, John Dramani Mahama President Nana Addo Dankwa Akufo-Addo and Former President, John Dramani Mahama

President of Policy think tank IMANI Africa, Franklin Cudjoe has expressed surprise about a seeming ‘brawl’ between the National Democratic Congress (NDC) and the ruling New Patriotic Party (NPP) over ownership of the recently commissioned Tema Motorway Interchange project.

Whilst the NDC maintains the project was kick-started by the NDC’s John Mahama in 2013, and so should be

Read full article



Facts

In 2013, the Government of Ghana under the John Dramani Mahama administration requested a grant from the Government of Japan to implement the project (The Tema Motorway Interchange).

The Japan International Cooperation Agency (JICA) then selected and dispatched a survey team which was headed by Mr. Ryohei Watanabe of CTI Engineering International Co., LTD. from March 2015 to March 2017.

According to FactCheckGhana.com, the initial survey and detailed designs were undertaken between March 2015 and December 2016 and the final report submitted to the Ministry of Roads and Highways for review and approval. This was also noted in the 2016 Budget Statement and Economic Policy of Ghana.



Although then-president John Dramani Mahama had mentioned in his 2016 State of the Nation address that “preparatory works for the redevelopment of the Accra-Tema motorway into a six-lane road with four interchanges at Adjei Kojo, Abattoir, Teshie Link, and Tema Roundabout will commence soon,” the project did not start until February 2018.

In 2017, the Government of Ghana signed grant agreements with the Japan International Cooperation Agency (JICA) to provide aid of up to a total of 6,459 million yen for two programmes in Ghana of which the Tema Motorway roundabout was included.



In December 2017, the Government of Ghana, the Ministry of Roads and Highways, and Shimizu-Dai Nippon JV signed a contract for the execution of the project. In February 2018, the vice president of Ghana, H.E Dr. Mahamadu Bawumia cut the sod for the commencement of the project.