Regional News of Wednesday, 29 May 2024

    

Source: Otec FM Online

Boankra Inland Port Project has been halted due to allegation of inflated cost of the project – Report

The agreed amount of 4 million dollars for earthworks reportedly ballooned to about 30 million The agreed amount of 4 million dollars for earthworks reportedly ballooned to about 30 million

The Boankra Integrated Logistics Terminal (BILT) project has been halted due to an alleged inflated cost for the first phase.

The agreed amount of 4 million dollars for earthworks reportedly ballooned to about 30 million dollars, causing a dispute between the Concessionaire and the Ministry of Transport.

The Ghana Shippers Authority brought in a consultancy company, Vision Consult, which failed to include the cost of earthworks in the project's designs.

After the contract was canceled, Ashanti Port Services Limited (APSL) filed a lawsuit against the Ghana Shippers Authority seeking damages amounting to over 3 billion US dollars.